Bodrum Municipality continues road improvement works on streets and avenues where infrastructure works by other institutions have been completed.

Teams from the Directorate of Public Works have recently completed hot asphalt works in Bitez and Torba neighbourhoods. In Bitez Neighbourhood, hot asphalt was laid by finisher on a 400-metre section of Pazar Street, covering an area of around 2,000 square metres.

In Torba Neighbourhood, works were carried out on Fatma Girik Street, 3003 Street, 13 Haziran Street, 3031 Street and Irmak Street. A total of 3,250 square metres of hot asphalt was laid across the five streets. With the completion of works in Bitez and Torba, around 5,250 square metres of road surface has been renewed.

Municipal teams currently continue asphalt works in Çamlık Neighbourhood in line with the planned programme.